2014-05-30 - 13072 - Rel Notes - EPM200 report #BIReleases2014
Release Notes
13072 - EPM200 report
Admin Info
Purpose
|
To create a parameter for customer selection on the EPM200 report.
|
Release No
|
001
|
Submitted
|
05/30/2014
|
Submitted by
|
Naga Brahmam
|
Source/Destination Systems
|
IT->BMS->QA folder to IT->BMS->Prod folder
|
Release Sent To
|
Mark Harris
|
Object(s) Created By
|
Naga Brahmam
|
Object(s) Tested By
|
Naga Brahmam
|
Report Name
EPM200 - Customer Segment Scorecard.
NEC Crystal Reports Standards Check
1. EPM200 has been successfully checked against the NEC Crystal Reports Standards Checklist.
2. EPM200 NEC CR checklist has been sent to NEC and also attached here for reference:
EPM200 NEC CR Standard Check List.xlsx
Release Notes
For Infrastructure
None
For Requestor
1. Created the customer prompt in both main and sub reports.
2. Linked the main report customer prompt with sub reports customer prompts.
3. Applied filter based on customer prompts in all the reports.
Test Notes
SNo.
|
Test Scenario
|
Expected Results
|
1
|
Report Format.
|
As per NEC standard checklist.
|
2
|
Scheduled the Report in NEC BI Launch Pad.
|
Report executed successfully in NEC BI Launch Pad.
|
Reference Document(Specification)
2014-05-30 - 13072 - Enhancement - EPM200 report